Union Pacific in Palm Springs

One of several daily Union Pacific freight trains rolling through north Palm Springs.

Blade Replacement 2023

Vestas V117 blade installation. The hub is 300′ above the ground.

Vestas V117 Blade Installation

A closer view of a 192-foot blade being installed on a Vestas V117 wind turbine, 2023.

GE 1.5 MW rotor

The rotor of a General Electric 1.5 MW wind turbine rests on the ground during a rotor service. Note the size relative to the crane. The nacelle cover rests on the ground behind the rotor.

GE Gearbox Replacement

A 13,000-pound planetary gearbox from a General Electric 1.5 MW wind turbine (installed 2011) is being lowered from the nacelle. The inset shows the scale and affords a better look at the crane, lifted into place by the service crane and mounted to the nacelle.